Construction is Powering Ahead
Mosaic Construction is continuing at full steam, with much work to be completed before the holiday break.
External scaffold removal is continuing on both the Arbor and Azure buildings, now sitting at levels five and two respectively, revealing each building’s spectacular form.
Your beautiful home in Azure is progressing wonderfully. Plasterboard sheeting has been complete to level seven, joinery installed up to level five, and the stone installed up to level three.
When on-site, there is already a very real sense of the ultra-luxuriousness of these extraordinary residences, and the view is utterly breathtaking. Photos just don’t do it justice.
Works are also progressing positively over in Arbor, with sheeting complete to level seven, and joinery and tiling installed to level four. The coming weeks will see a busy run into Christmas, with much still to be achieved!